Penny Place construction progress update for April:
- Level 5 & 6 slabs poured
- Ground floor blockwork finished
- Ground Floor (Nelson Street) feature brickwork now complete
- Level 1 blockwork now complete
- Level 7 formwork now complete
- Fire Sprinklers to Level 3 now complete
- Precast cores to Level 6 installed
- Carpark screens to Level 1 to 3 works commenced