Penny Place construction progress update for April:  

  • Level 5 & 6 slabs poured
  • Ground floor blockwork finished
  • Ground Floor (Nelson Street) feature brickwork now complete
  • Level 1 blockwork now complete
  • Level 7 formwork now complete
  • Fire Sprinklers to Level 3 now complete
  • Precast cores to Level 6 installed
  • Carpark screens to Level 1 to 3 works commenced

Ever wondered what your Penny Place apartment will look like? 

Watch our 3D Video Fly-Th ru below. https://www.facebook.com/UtopiaPropertyDeveloper/videos/708615339964220/?epa=SEARCH_BOX